top of page

Program Management

Overall Project Management and Leadership

THL provides your solid foundation for a successful project. The various other project team members on large scale construction projects are only involved in some of the project phases. Having an Overall Project Manager provides continuity from the initial conceptual phase to construction completion. This typically reduces the overall project costs by 5-10%

Frankfort Family, Reena Residence

155/65 Elm Ridge, Toronto

This $65 million project is a 120,000 sf, 106 unit, 19 storey rental building.  THL was contacted by the Owner to assist in obtaining the Zoning Bylaw Amendment and Site Plan Approval. Working with the lead architect, after 4 months, the first full Site Plan Application was submitted and then work progressed through the City review comments. The Zoning Bylaw Amendment was obtained after 12 months, and work is wrapping up on obtaining the Notice of Approval with Conditions. THL issued Requests for Proposal and recommended a number of the project consultants.

New Rental Building

55 Erskine Ave, Toronto

This $70 million project is a 100,000 sf, 103 unit, 11 storey rental building. THL was contacted by the Owner to assist in resolving the final design issues to obtain the Notice of Approval with Conditions. It is a new rental building on the same property as the original rental building. THL focused on addressing the key City and design issues and the NOAC was issued 6 months after we began work.  THL is now working with the Owner to resolve the NOAC conditions and complete the Parkland Dedication so that construction can proceed shortly.

Picture1thl2.png

Lakeshore Pointe Master Plan

55 Thompson, North Bay

THL was contacted by the Owner to finalize the details related to their five phase master plan for the Lakeshore Pointe development. Phase 1 sales are underway and the design is completed. Phases 2 to 5 are now being reviewed to determine the optimum use of the property.  The current concept includes a 70 unit condominium (Phase 1 underway), townhouses, semi-detached homes, single family dwellings, and three additional condominium towers.  It is envisioned that the design and construction will proceed over the next 6-8 years.

600Dixon.png

Regal Plaza

600 Dixon Road, Toronto

This $100 million project is 11 stories and 230,000 SF. Staff of THL assisted the Developer in taking his highly conceptual idea and progressing through the Site Plan Application process to achieve the required approvals and permits for construction. We retained the consultants to prepare the documents required for the Site Plan Application, plus the Construction Manager.

Lakeshore Pointe Phase 1

55 Thompson, North Bay

This $33 million project is a 70,000 sf, 70 unit, 4 storey condominium. THL was contacted by the Owner to assist in resolving the final design issues and then proceed with sales, then construction. THL immediately completed a Value Engineering exercise which substantially reduced the project cost while improving the solution. Meetings were held with the City to confirm their acceptance of the changes, then condo sales began 4 months after THL commenced.  THL was heavily involved in the design improvements, condo sales materials, funding, and all other aspects of the project.  We also retained the remaining consultants to finalize the design.

Picture1.png

Rental Building Replacement

1996-2000 Bathurst, Toronto

This $55 million project is two buildings, 7 stories, 112 units, and 110,000 SF. THL is the Program Manager overseeing the final design and then construction of Building A. In parallel, the site plan approval process is proceeding on Building B.  The scope includes demolishing the smaller older buildings then constructing the two new larger buildings with underground parking.

Program Management: Products
Screen Shot 2022-11-30 at 4.17.31 PM.png

New Rental Building​

515 Chaplin Ave, Toronto​

This $52 million project is a 60,000 sf, 66 unit, 13 storey rental building. THL was contacted by the Owner to assist in resolving the final design issues to obtain the Zoning Bylaw Amendment and Notice of Approval with Conditions. It is a new building on the same site as an existing rental property. One challenge was that the construction cost was too high to justify proceeding. THL completed a Value Engineering exercise which substantially reduced the project cost while improving the solution. An improved design was submitted to the City after 5 months and the ZBA was issued after 10 months. ​

pinewood.png

Pinewood Studio Expansion

225 Commissioners Street,Toronto

This $55 million project was three separate buildings for a total of 200,000 SF. The client was concerned about potential increased construction costs which would make the project financially unviable. THL recommended a methodology for confirming construction costs, enabling Value Engineering workshops, and verifying targeted project payback. The entire assignment was completed in less than four months.

backstage_edited.jpg

Backstage on the Esplanade

1 the Esplanade, Toronto

This $125 million project was 36 stories and 350,000 SF, including 6 levels of underground parking. Staff of THL became involved when the project was only 30% complete and well over budget and schedule. First, the critical issues delaying construction were resolved and then the project was finished on schedule and budget.

l_tower_edited.jpg

L Tower

8 the Esplanade, Toronto

This $236 million project was 60 stories and 500,000 SF. Staff of THL became involved when the project was 80% complete and well over budget and schedule. First, the critical issues delaying construction were resolved and then the project finished. This involved resolving over 10 lawsuits and collecting over $1.5 million from these lawsuits to increase the project profit.

brampton.png

Brampton City Hall & West Tower

41 George St. Brampton

This $94 million project was 9 stories and 220,000 SF. The previous project staff were unable to resolve over 1,100 remaining design and construction issues. Implementing the Project Closer methodology, Staff of THL organized, investigated, then resolved all of the development, design and construction issues to bring this project to closure.

bottom of page